Feb 242022
 

Return to ITER Power Facts Main Page

By Steven B. Krivit
Feb. 24, 2022

Dear Dr. Bigot,

I noted with interest your letter today responding to our news story published Feb. 21, 2022, “French Regulator Halts Assembly of ITER Reactor.”

You wrote, “Recently some misinformation has circulated at the initiative of a few well-known anti-hydrogen-fusion activists regarding the status of the ASN (Autorité de sûreté nucléaire) oversight of the ITER project.”

You further wrote, “Contrary to what has been claimed by these anti-ITER fellows using social media, the ASN has not shut down ITER construction.”

New Energy Times first reported this story on Monday. Daniel Clery of Science reported the news today. Clearly, you must be referring to us. But New Energy Times did not say that construction at the ITER site had been shut down. I’m certain that there are lots of construction activities at your site. The focus of our article, as our title says, is a halt of the assembly of the reactor.

You wrote, “There have also been claims that the vacuum vessel sectors were dropped – also false.”

Well, sir, I would kindly direct you to what we reported on Monday:

As New Energy Times reported on Nov. 10, 2021, both of the vacuum vessel sectors that have been delivered to the ITER site were damaged during manufacture. Either the sectors or parts of the sectors (details are unclear) fell at the manufacturing sites and sustained dimensional distortion, according to ASN.

Here’s what we reported three months ago based on the July 2, 2021, ASN ITER Inspection Report #INSSN-MRS-2021-0650:

In the report, the most serious issue identified by the inspectors was that parts of two very large components, sectors of the vacuum vessel, fell during manufacturing and sustained damage. The ASN report does not provide details of the damage.

The report also states that inspectors discovered the forgery of certificates of welder qualifications, found gaps in welds, and detected leaks in cooling tower basins. Inspectors wrote that one of the areas at the reactor construction site was not accessible to them on the day of the inspection. Inspectors also noted unsatisfactory responses to their requests for documents from the ITER organization.

Here are the key parts of what the ASN document INSSN-MRS-2021-0650 says, first in French, then translated to English:

Part 1

Les inspecteurs ont notamment examiné par sondage le traitement des écarts et des modifications ainsi que les suites des chutes d’éléments de secteurs de la chambre à vide lors de leur manutention sur des sites de fabrication en Corée du Sud et en Italie. La découverte de falsification de certificats de qualifications de soudeurs, à la suite d’une information d’alerte de l’ASN, a également fait l’objet de vérifications.

In particular, the inspectors examined on a test basis the treatment of deviations and modifications as well as that the consequences of the falls of elements of sectors of the vacuum chamber during their handling on manufacturing sites in South Korea and Italy. The discovery of forgery of certificates of welder qualifications, following an alert from ASN, was also the subject of checks.

Part 2

Chute d’éléments de secteurs de la chambre à vide: Des éléments de secteurs de la chambre à vide ont chuté lors de manutention sur les sites de fabrication, en Corée du Sud en avril 2021 et en Italie en mai 2021.

Falling elements of sectors of the vacuum chamber: Sectors of the vacuum chamber fell during handling on the manufacturing sites, in South Korea in April 2021 and in Italy in May 2021.

More important is that the ITER Organization accepted delivery of these two damaged sectors more than eight months ago. ASN advised you of the damage eight months ago. In response, you continually asked ASN to accept your alternate installation plan and to release the hold point. ASN has repeatedly declined your request to release the hold. Finally, in a meeting on Jan. 5, 2022, ASN specifically instructed you not to proceed unless you could remove the sectors from the pit.

Your Web site says that insertion of the first sector was to take place in December 2021. So assembly of the reactor vessel has been on hold for two months. And you did not share this information publicly.

As always, we take journalistic integrity seriously and welcome any letter identifying any error of fact or context or any significant omission in New Energy Times.

Kind regards,
Steven B. Krivit


Feb. 28: 2022: ITER Organization Releases Statement

Feb 242022
 

Return to ITER Power Facts Main Page

By Steven B. Krivit
Feb. 24, 2022

On Monday, New Energy Times published “French Regulator Halts Assembly of ITER Reactor.”

Today, Bernard Bigot, the director-general of the ITER organization, sent the following letter to ITER staff members. Several of them sent us copies of the letter, which we have reproduced, unedited, below.

See our response here.


 

From: Bigot Bernard <Bernard.Bigot@iter.org>
Sent: 24 February 2022 14:00
To: only-staff <only-staff@iter.org>; All-IPA <All-IPA@iter.org>
Subject: FW: Message to All-ITER regarding ongoing activities with ASN, the French safety regulator

Dear Colleagues,

For those of you who are not yet aware, I would like to inform you that the IO has received a letter from the French Nuclear Regulator (ASN, Autorité de sûreté nucléaire) dated 25 January 2022 in response to our request, dated 1 February 2021, for authorization to start assembling Tokamak equipment inside the cryostat (welding of the first two vacuum vessel sectors). The purpose of our request was to get the release of the Hold Point decided in November 2013 by ASN for checking as-built performances of the B2 slab supporting the Tokamak Complex Building. This is normal procedure after ASN validated the proposed ITER design in 2012 and signed the “décret d’autorisation de creation” of ITER as a nuclear installation in 9 November 2012.

After many meetings at technical levels with ASN and IRSN (its technical supporting organisation) during the year 2021/early 2022, ASN considered that there were still some points that require complementary analysis and safety demonstration. They are mainly related to radiation protection measures, confirmation of the as-built masses supported by the slab and their impact on the mechanical resilience of the slab in extreme conditions, and qualifications of the process of the vacuum welding after due consideration of some geometrical non-conformities of the sectors interfaces that we had detected.

We immediately set up a IO task force with all the stakeholders to address the complementary requests from ASN before they would be able to release the hold point for Tokamak assembly. Our roadmap is to provide IO key answers before the end of April 2022 in such a way ASN could assess them and decide about the release without impacting the ITER schedule for installation of the sectors.

Recently some misinformation has circulated at the initiative of a few well-known anti-hydrogen-fusion activists regarding the status of the ASN (Autorité de sûreté nucléaire) oversight of the ITER project. It is important for all ITER staff and collaborators to be reassured regarding this issue.

Contrary to what has been claimed by these anti-ITER fellows using social media, the ASN has not shut down ITER construction – as anyone at ITER may find quite evident by observing the broad range of successful activities progressing every day across the worksite, at the highest standards of quality and safety. There have also been claims that the vacuum vessel sectors were dropped – also false. While some nonconformities have been identified with the vacuum vessel sectors (see above), as noted in the ASN letter, these are technical challenges for which we will provide safe, high quality engineering solutions. Given the unprecedented technical specifications for ITER’s many First-of-a-Kind components, which we are combining into a First-of-a-Kind machine, some such nonconformities and technical challenges are to be expected – and in fact, over the past 7 years and more, we have overcome many technical challenges, and we will continue to do so.

Please do not be distracted by these types of false claims. The One-ITER team – all of you – should feel absolutely proud of the amazing work that has been performed so far, the work being performed every day, and our determination to face the challenges that lie ahead. I ask you never to lose sight of the ultimate goal: we are committed to deliver the ITER facility as a demonstration of the feasibility of fusion power to provide safe, environmentally friendly, and virtually unlimited energy for future generations.

With gratitude for your continued strong efforts on behalf of the ITER project,

Warmest regards,

Bernard


See our response here.

Feb 192022
 

Feb. 19, 2022

Celia Dugger, Science Editor
Pui-Wing Tam, Technology Editor
Michael Roston, Deputy Technology Editor

Dear Editors,

In several news articles, the New York Times has published inaccurate information about the purpose and primary design objective of the International Thermonuclear Experimental Reactor (ITER).

Examples:
  • “If successful, the reactor would ignite a fusion reaction and produce up to 1.5 billion watts of power, demonstrating the feasibility of exploiting hydrogen fusion for large-scale power generation.” (Malcolm Brown— Dec. 10, 1996)
  • “ITER, a $10 billion project intended to demonstrate by the year 2008 that hydrogen isotope fusion, a process somewhat similar to that which powers the sun, could be a commercially practical source of energy.” (Malcolm Brown— May 20, 1997)
  • “ITER would provide a record 500 megawatts of fusion power for at least 500 seconds, a little more than eight minutes, during each experiment. That would meet the power needs of about 140,000 homes.” (Robert Stern — 31, 2003)
  • “The goal is to prove that energy can be generated through nuclear fusion … So far, experimental fusion reactors have required more energy to operate than they have produced. ITER and the project in Japan are supposed to prove that fusion could be much more than a drain on the grid. … Scientists then would spend the next decade or so trying to create bursts of power of up to 500 megawatts for several minutes at a time.” (James Kanter — April 29, 2009)
  • “Although all fusion reactors to date have produced less energy than they use, physicists are expecting that ITER will benefit from its larger size, and will produce about 10 times more power than it consumes.” (Henry Fountain — March 27, 2017)
  • “The [ITER] consortium hopes to begin generating electricity at the site in 2035. … So far, the best effort to reach positive energy output from a fusion reactor was achieved by the Joint European Torus, or JET, project, a Tokamak that began operation in 1983 in Oxfordshire, England. The device was able to produce 16 megawatts of fusion power while consuming 24 megawatts.” (John Markoff, Aug. 11, 2021)
  • “In the late 1990s, the Joint European Torus experiment in England was able to generate 16 million watts of fusion power for a brief moment, going about 70 percent of the way to producing as much power as it consumed.” (Kenneth Chang — Aug. 17, 2021)
ITER Power Facts

ITER is designed to inject 50 megawatts of heating power into the fuel to create a fusion plasma with 500 megawatts of thermal power. That is its primary scientific purpose and design objective, according to the ITER Design Specification published by the International Atomic Energy Agency in 2002.

If ITER accomplishes that objective, the overall reactor will use at least 300 megawatts of electricity continuously throughout the experiment. Since 2017, some fusion scientists have started saying that the ITER reactor will need 50 megawatts to start the reaction. That is not the same as the power needed to start the reactor, which is 500 megawatts of electricity.

On this Web page, I list 11 sources that describe the operating power requirement for ITER in the 300-megawatt range. I list three references that are in the 400-megawatt range.

These facts mean that the overall ITER reactor, if it works as designed, will not produce net power or net energy.

JET Power Facts

The ITER power discrepancy was a direct successor to the JET power discrepancy. Here’s an example of the false power claims about JET, published on March 12, 2018, in the Guardian: “[JET] remains the gold standard for fusion power – but it achieved just 16 MW of output for 25 MW of input.”

JET’s 1997 result still holds the record for power output. But the 16-megawatt output needed an input of 700 megawatts. Full technical details about both reactors are here.

For Your Readers 

The ITER organization claims that the ITER reactor will “prove that fusion power can be produced on a commercial scale and is sustainable.” It says that the project “aims to demonstrate that it is possible to produce commercial energy from fusion.”

With a projected net power loss for the overall reactor, the upper management of the organization knows that they cannot possibly deliver such promises.

Perhaps your readers would appreciate learning the facts now.

Steven B. Krivit
Publisher and Senior Editor, New Energy Times

 

 

Feb 182022
 

Feb. 18, 2022

Richard Webb, Executive Editor, New Scientist
Emily Wilson, Editor, New Scientist

Dear Editors,

In several news articles, New Scientist has published inaccurate information about the purpose and primary design objective of the International Thermonuclear Experimental Reactor (ITER).

Examples:
  • “For 50 MW of input power, ITER will generate 500 MW of output power.” (Roger Highfield, Valerie Jamieson, Neil Calder and Robert Arnoux, Oct. 9, 2009)
  • “[ITER is] aiming to get about 10 times more energy out of the fusion reaction than they put in. That will prove fusion energy is possible.” (Sean O’Neill quoting Melanie Windridge, Sept. 15, 2018)
  • “That might change in 2025, when the world’s biggest fusion project, ITER in France, is due to switch on. The hope is it will turn 50 megawatts of power into 500MW, proving a net gain is possible.” (Adam Vaughan, Dec. 2, 2020)
  • “The plan is to create 500 megawatts of usable energy from an input of 50 megawatts.” (Matthew Sparkes, June 15, 2021)
ITER Power Facts

ITER is designed to inject 50 megawatts of heating power into the fuel to create a fusion plasma with 500 megawatts of thermal power. That is its primary scientific purpose and design objective, according to the ITER Design Specification published by the International Atomic Energy Agency in 2002.

If ITER accomplishes that objective, the overall reactor will use at least 300 megawatts of electricity continuously throughout the experiment. Since 2017, some fusion scientists have started saying that the ITER reactor will need 50 megawatts to start the reaction. That is not the same as the power needed to start the reactor, which is 500 megawatts of electricity.

On this Web page, I list 11 sources that describe the operating power requirement for ITER in the 300-megawatt range. I list three references that are in the 400-megawatt range.

These facts mean that the overall ITER reactor, if it works as designed, will not produce net power or net energy.

JET Power Facts

The ITER power discrepancy was a direct successor to the JET power discrepancy. Here’s an example of the false power claims about JET, published on March 12, 2018, in the Guardian: “[JET] remains the gold standard for fusion power – but it achieved just 16 MW of output for 25 MW of input.”

JET’s 1997 result still holds the record for power output. But the 16-megawatt output needed an input of 700 megawatts. Full technical details about both reactors are here.

For Your Readers 

The ITER organization claims that the ITER reactor will “prove that fusion power can be produced on a commercial scale and is sustainable.” It says that the project “aims to demonstrate that it is possible to produce commercial energy from fusion.”

With a projected net power loss for the overall reactor, the upper management of the organization knows that they cannot possibly deliver such promises.

Perhaps your readers would appreciate learning the facts now.

Steven B. Krivit
Publisher and Senior Editor, New Energy Times

 

Feb 172022
 

Feb. 17, 2022

John Mulholland, Editor, Guardian U.S.
Katharine Viner, Editor-in-Chief
Kerry Eustice, Managing Editor
Merope Mills, Executive Editor
Regina Buckley, President of Guardian US

Dear Editors,

In several news articles, the Guardian has published inaccurate information about the purpose and primary design objective of the International Thermonuclear Experimental Reactor (ITER) and the Joint European Torus (JET) fusion reactor.

Examples:
  • “In 1991, scientists at JET became the first in the world to produce energy from a deuterium/tritium plasma. While JET generated 16 MW of power, ITER is designed to produce some 500 MW in 400-second bursts.” (Ian Sample, Jan. 29, 2009)
  • “Cowley is referring to the moment of parity when the amount of energy they extract from a tokamak equals the amount of energy they put into it. At present, the best-ever “shot” – as the scientists refer to each fusion reaction attempt – came in 1997 when, for just two seconds, the JET (Joint European Torus) tokamak at Culham achieved 16MW of fusion power from an input of 25MW. … ‘We could produce net electricity right now, but the costs would be huge,’ says Cowley. … ITER which, it is hoped, will demonstrate the commercial viability of fusion by producing a tenfold power gain of 500MW during shots lasting up to an hour.” (Leo Hickman, Aug. 23, 2011)
  • “[ITER’s] design is a scaled-up version of JET, and the scientists here want to produce 500 megawatts of power, 10 times its predicted input.” (Alok Jha, Jan. 25, 2015)
  • “ITER should be completed in 15-20 years and claims to deliver 500 MW of power, about the same as today’s large fission reactors.” (Damian Carrington, Oct. 17, 2016)
  • “‘We are convinced we can deliver hundreds of megawatts through ITER,’ up to 10 times more energy than is put in, says David Campbell.” (Damian Carrington, Dec. 2, 2016)
  • “JET hasn’t even managed to break even, energy-wise. Its best ever result, in 1997, remains the gold standard for fusion power – but it achieved just 16 MW of output for 25 MW of input.” (Editors, March 12, 2018)
  • “In 1997 JET set a world record for the highest ratio of energy out to energy in. But that was still just two-thirds of the break-even point where the reactor isn’t consuming energy overall. … [ITER] hopes to conduct its first experimental runs in 2025, and eventually to produce 500 megawatts (MW) of power – 10 times as much as is needed to operate it.” (Philip Ball, Oct. 27, 2019)
  • “ITER project will replicate the reactions that power the sun and is intended to demonstrate fusion power can be generated on a commercial scale. … The ITER project will be the first to achieve a “burning” or self-heating plasma and is expected to generate 10 times more heat than is put in, far more than any previous attempt.” (Damian Carrington, July 28, 2020)
ITER Power Facts

ITER is designed to inject 50 megawatts of heating power into the fuel to create a fusion plasma with 500 megawatts of thermal power. That is its primary scientific purpose and design objective, according to the ITER Design Specification published by the International Atomic Energy Agency in 2002.

If ITER accomplishes that objective, the overall reactor will use at least 300 megawatts of electricity continuously throughout the experiment. Since 2017, some fusion scientists have started saying that the ITER reactor will need 50 megawatts to start the reaction. That is not the same as the power needed to start the reactor, which is 500 megawatts of electricity.

On this Web page, I list 11 sources that describe the operating power requirement for ITER in the 300-megawatt range. I list three references that are in the 400-megawatt range.

These facts mean that the overall ITER reactor, if it works as designed, will not produce net power or net energy.

JET Power Facts

The ITER power discrepancy was a direct successor to the JET power discrepancy. Here’s an example of the false power claims about JET, as you published on March 12, 2018: “[JET] remains the gold standard for fusion power – but it achieved just 16 MW of output for 25 MW of input.”

JET’s 1997 result still holds the record for power output. But the 16-megawatt output needed an input of 700 megawatts. Full technical details about both reactors are here.

For Your Readers 

The ITER organization claims that the ITER reactor will “prove that fusion power can be produced on a commercial scale and is sustainable.” It says that the project “aims to demonstrate that it is possible to produce commercial energy from fusion.”

With a projected net power loss for the overall reactor, the upper management of the organization knows that they cannot possibly deliver such promises.

Perhaps your readers would appreciate learning the facts now.

Steven B. Krivit
Publisher and Senior Editor, New Energy Times

 

© 2025 newenergytimes.net